Council adopts a Capital Works Budget each year to ensure our assets are well maintained. As part of Council's 2024/25 Capital Works Budget, $21.9 million is invested in upgrades and renewals of our extensive road and transport network to benefit our community.
In addition to specific projects, Council also includes larger regional projects such as the Regional Bitumen Reseal Program and Regional Gravel Resheet Program to ensure we renew our transport infrastructure assets to keep them in good condition.
Regional Bitumen Reseal Program
This ongoing program involves renewing the bitumen seals across the existing road network. Various sites are selected for reseal according to the condition rating and bitumen seal age. In the 2024/25 budget, $3.75 million has been allocated to the program.
- A McIntyre's Road, Chinchilla
- D McIntyre's Road, Chinchilla
- Greenswamp Road, Chinchilla
- Inverai Road, Chinchilla
- Lee's Road, Chinchilla
- Muller's Road, Chinchilla
- Oak Park Road, Chinchilla
- Scouller's Road, Chinchilla
- The Peak Road, Chinchilla
- Widdon's Road, Chinchilla
- Barnsley Street, Chinchilla
- Dorney Street, Chinchilla
- Edward Street, Chinchilla
- Helena Street, Chinchilla
- Mackie Street, Chinchilla
- McKenzie Street, Chinchilla
- Pilkington Street, Chinchilla
- Dudley Street, Chinchilla
- Agnes Street, Dalby
- Ayrton Street, Dalby
- Lynette Street, Dalby
- Butlers Road, Miles
- Fairymeadow Road, Miles
- Freemans Road, Miles
- Hookswood - Pelham Road, Miles
- Roxborough Road, Miles
- Ryalls Road, Miles
- Yulabilla Road, Miles
- Bennetts School Road, Tara
- Community Lane, Tara
- Flinton Road, Tara
- Glenern Road, Tara
- Goranba Lane, Tara
- Humbug Road, Tara
- Males Drive, Tara
- Mary Road, Tara
- McKenzies Road, Tara
- Millers Road, Tara
- New Settlers Road, Tara
- Old Coomrith Road, Tara
- Timothy Road, Tara
- Tregathlyn Road, Tara
- Upper Humbug Road, Tara
- Western Road, Tara
- Baddleys Lane, Tara
- Binnie Street, Tara
- Old Hospital Road, Tara
- Yaralla Wheat Road, Dalby
Regional Gravel Resheet Program
The Gravel Resheet Renewal Program focuses on renewing the pavement across the existing unsealed gravel road network. Council has allocated $5 million in the 2024/25 budget for the program.
Regional Road Resilience Program
Council has allocated $1 million in the 2023/24 budget for the Regional Road Resilience Program. This project focuses on upgrading vulnerable assets to more resilient assets, such as floodways. This project is a special initiative to fund ‘build back better’ projects identified through the delivery of the 2021/22 Flood Damage Restoration Program.

Please see below the adopted transport asset projects included as part of Council’s 2024/25 Capital Works Program.
- Glenern Road, Glenmorgan Ch 20.551 (existing bitumen) - 29.988km (MRC boundary) - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Willacy St, Wandoan, Weldon St to Longford St - New Concrete Footpath
- Bundi Road, Wandoan Ch 39.097 (existing bitumen) - 43.998km (Clifford Road) - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Dulacca South Road, Dulacca Ch 16.1 - 22.6km - Road Reconstruction and Widening
- Commodity Court, Dalby - Road Reconstruction
- Windmill Road (0 - 0.623) - Road Reconstruction including Kerb and Channel Upgrade
- Little St, Chinchilla Ch 0 - 0.162 - Road Reconstruction including Kerb and Channel Upgrade
- Kupunn - Duleen Road, Kupunn Ch 0 - 2.3km - Road Reconstruction
- Old Moonie Road, Moonie Ch - Gravel Resheet incorporating Flood damage
- Burra Burri - Darr Creek Road, Burra Burri Ch 8.5 - 10km - Road Reconstruction
- Burra Burri Creek Road, Fairyland Ch 27.8 - 30km - Road Reconstruction
- Cambridge Crossing Road, Tara Ch 26.2 - 27.4km - Road Reconstruction and Widening
- Slessar St, Chinchilla, Hospital to Bull Dog Park - New Concrete Footpath
- Stiller St, Wandoan, North St to Weldon St - New Concrete Footpath
- Weldon St, Wandoan, Stiller St to Willacy St - New Concrete Footpath
- Wheeler St (0 - 0.424) - Reconstruct inc Kerb and Channel Upgrade in sections
- Old Rosevale Road, Jandowae Ch 17 - 18.7km - Road Reconstruction
- Redmarley Road, Condamine Ch 0 (Leichhardt Hwy) - 3km - Road Reconstruction and Widening
- Roche Creek Road, Wandoan Ch 15.5 (Bungaban Road) - 17.21km - Road Reconstruction and Widening
- Upper Humbug Road, Tara Ch 12.840 to 19.107 - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Dorney St (0 - 0.473) road reconstruction inc Kerb and Channel Upgrade in sections
- Myall Park Road and Retreat Road intersection realignment and upgrade from unsealed gravel pavement to bitumen seal
- Apelts Road, Southwood 15km - Gravel Resheet and Flood Damage Restoration
- McCaskers Road, Tara Ch 0.085- 5.10 - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Surcingle Road (2640 to 2840) Bitumen Dust Suppression
- Brigalow - Canaga Road, Brigalow, Ch 5.03 - 8.5 - Road Reconstruction
- Brigalow Street, Jandowae Ch 0.23 - 0.29 - Bitumen Dust Suppression
- Brigalow Street, Jandowae Ch 0.37 - 0.46 - Bitumen Dust Suppression
- Elerslea Lane East Road, Condamine - Flood Damage Restoration
- Turner Street, Chinchilla Ch 0 - 0.15 - Road Reconstruction inc Kerb and Channel Upgrade
- Leichhardt Avenue (Lawson St to Black St), Dalby Ch 0.234 - 0.465 - Road Reconstruction
- Curtis Street, Dalby Ch 2.073 - 2.643 - Road Reconstruction inc Kerb and Channel Upgrade
- Kent's Road, Jimbour Ch 2.5 - 4.04 - Road Reconstruction
- King's Road, Bell Ch 1.01 - 1.49 - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Roche Creek Road, Roche Creek Ch 9.5 - 13.86 - Road Widening & Reconstruction
- Wills Place, Dalby Ch 0.0-.125 - Road Reconstruction inc Drainage improvements
- Mt Myrtle Road, Mt Myrtle - Bitumen Dust Suppression
- Hill St, Jandowae, Coxen St (Ch 0) to Ch 277m - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Coxen St, Jandowae, Albert St to Hill St - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Jandowae Pool Access, Jandowae existing bitumen (Ch 344) to Ch 500m - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Dawson Street Service Road, Miles Ch 0.01 - 0.310 Parking Lane upgrade from unsealed gravel pavement to bitumen seal
- Malduf St, Chinchilla - New Underground Stormwater
- Price St, Chinchilla, Fraser St to Zeller St - New Concrete Footpath
- Robinson St, Warra, Lytton St to Thorn St - New Concrete Footpath
- Sandalwood Ave East, Dalby, Branch Creek Road to Southern Cross Drive - New Concrete Footpath
- Thorn St, Warra, Hall to Raff St - New Concrete Footpath
- Booral Road, Wandoan Ch 2.65 - 5.69km - Road Reconstruction
- Clifford Road, Wandoan Ch 3 (existing bitumen) - 13.75km (Bundi Road) - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Cuddihy St, Brigalow, Ch 0 - 0.287km - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Dickman St, Chinchilla Ch 0 - 0.12km - Road Reconstruction including kerb and channel upgrade
- Evans St, Chinchilla, Ch 0 - 0.597 - Road Reconstruction including kerb and channel upgrade
- Fraser St, Chinchilla Ch 0 - 0.198 - Road Reconstruction including kerb and channel upgrade
- Gaske St, Chinchilla Ch 0 - 0.221 - Road Reconstruction including kerb and channel upgrade
- Woollett's Road, Jandowae (1.5 - 2.0) - Road Reconstruct
- Woollett's Road, Jandowae (3.486 - 7.799) - Upgrade from Unsealed Gravel Pavement to Bitumen Seal
- Wambo Street (0.36 - 0.481) - Dust suppression Extension
- Wambo Street (00- 0.16;) - Dust suppression Extension
- Grosmont Road, Grosmont Ch 10.2 - 10.4km - Bitumen Dust Suppression
- Grosmont Road, Grosmont Ch 7.395 - 7.6km - Bitumen Dust Suppression
- Grosmont Road, Grosmont Ch 9.3 - 9.5km - Bitumen Dust Suppression
- Hayden St, Dalby - Blaxland Road to Winton St - Gravel Resheet Works including Flood Damage
- L Road, Wandoan Ch 4 - 4.6km - Bitumen Dust Suppression
- Southwood Road, Hannaford Ch 17 - 22.2km - Road Reconstruction and Widening
- Springvale Road, Springvale Ch 13 - 14km - Road Reconstruction
- Mary Street, Dalby - Stormwater Upgrade Project (Delivery of storm water componentry complete)